Fort Hills Mine Site
Deep Undergrounds Project

mining project
Capital cost:

Scope duration:

Leadership team size:

Contract type:

Owner:


Contractor Client:

Project Site Office:
$11.0M

9 months (2012)

20 crew size

CCDC 4

Suncor


Clark Builders

Fort Hills Mine Site, Fort Hills, AB

Deep Undergrounds

The Scope of the Works

Additional scope was added to the core building competition project and this was the primary and secondary water supply lines, fire line and sewer lines. This was classified as “deep underground” as the trenches were at minimum 6m in depth.

Works Program

This work was performed at the same time that the scope of the services installation was being undertaken underneath the prefabricated dormitories that were supplied to sit on a previously driven pile foundation.